Required Dwelling Inspections
** PLEASE NOTIFY THE BUILDING OFFICIAL’S OFFICE AT LEAST ONE DAY IN ADVANCE BEFORE INSPECTION IS NEEDED AND ALSO GIVE A PERMIT NUMBER **
TEMPORARY POWER POLE
If needing temporary power pole, try to have it put up and ready for inspection at the same time as the footer inspection, if not there will be an extra charge.
FOOTING INSPECTION
After footing is dug or formed, and reinforcing steel is in place, before the concrete is poured.
SLAB
After slab is dug or formed, and reinforcing steel is in place, before the concrete is poured.
FOUNDATION WALLS
After all walls are laid up or poured walls are in place, water proofing and french drains are in place, and before back filling.
ROUGH - IN’S
When electrical wiring, plumbing fixtures, and hvac are roughed in. Please do not cover any wiring or plumbing or hvac before this inspection has been made.
FRAMING
After all wood or metal framing is complete.
INSULATION
Insulation inspection will need to be done after all Rough-In has been inspected.
ELECTRICAL
The Building Official is required to inspect the electrical system before American Electric Power will connect the service.
FINAL
A final inspection is required after the dwelling is completed.
** ADDITIONAL INSPECTIONS MAY BE REQUIRED **
USBC 113.4 Additional inspections.
The building inspector may designate additional inspections and tests to be conducted during the construction of a building or structure and shall so notify the permit holder.